Project Description
Introduction
Project Name: MAJ Track Off & On
Customer Organisation: J. Murphy & Sons LTD.
Customer Contact Details: Mr Stuart Williams, Project Manager
Value: £58,000
Schedule of Works
GBR Solutions was contacted through J Murphy & Sons to provide works at Victoria Station, Manchester to remove track and reinstate with new track and stressed on underbridge due to refurbish works on bridge foundations.
These works were carried out over 3 shifts where we successfully integrated various disciplines including Signalling, Civils and RRV’s
Collaboration was key to our success in delivering this small project within the limited timescales over the Christmas period and resulting in improved water membrain bridge repairs. I am also delighted to report that under these unprecidented times of Covid, these works were carried out utilising local resources and cross-hiring equipment from our local supply chain.
These works were carried out over 3 shifts where we successfully integrated various disciplines including Signalling, Civils and RRV’s
Collaboration was key to our success in delivering this small project within the limited timescales over the Christmas period and resulting in improved water membrain bridge repairs. I am also delighted to report that under these unprecidented times of Covid, these works were carried out utilising local resources and cross-hiring equipment from our local supply chain.
Key Project Facts
- 60 feet of plain line track was removed and replaced
- 30 insulated block joints installed
- Local resources utilised
- Equipment sourced locally via Supply Chain
- Client supplied machines
- Government guidelines was communicated and strictly monitored throughout